What Is Air Changes Per Hour (ACH)?

Air Changes Per Hour (ACH) expresses how many times the total room air volume is replaced by fresh outdoor air each hour. It is the standard basis for industrial ventilation design because it is directly linked to room volume, required airflow, and the number of occupied persons per hour.

For factory ventilation, ACH values are set by occupational health standards, process requirements, and room type. A typical light assembly factory might require 6 ACH, while a chemical process workshop with high fume generation may need 20-30 ACH.

The Core Formula

The fundamental relationship between ACH, room volume, and fan airflow is:

Required Airflow (Q) = ACH × Room Volume ÷ 60

Where:

  • Q — fan total airflow in m³/h (or m³/min)
  • ACH — target air changes per hour (from standard or process requirement)
  • Room Volume (V) — in m³ (length × width × ceiling height)
  • 60 — conversion from hours to minutes if airflow is in m³/min

Step-by-Step Calculation

Step 1: Measure the room. Record the floor length (L), width (W), and ceiling height (H) in metres. Calculate room volume: V = L × W × H. For multi-bay or mezzanine rooms, calculate each zone separately.

Step 2: Determine target ACH. Refer to applicable national or industry standards. Common reference values:

  • Light assembly / electronics: 6-10 ACH
  • General machining / fabrication: 10-15 ACH
  • Welding / grinding: 15-25 ACH (plus local extraction at each station)
  • Chemical / solvent processes: 20-30+ ACH (often with point-of-source capture)
  • Paint spray / finishing: 25-40 ACH (check flammable solvent vapour limits)

Step 3: Calculate required total airflow. Q_total = ACH × V. For example, a workshop 30 m × 20 m × 6 m = 3,600 m³, at 12 ACH → Q_total = 43,200 m³/h. For fresh air supply only, use 60 to convert: Q_total_min = 43,200 ÷ 60 = 720 m³/min.

Step 4: Distribute airflow across fans. Add a 10-20% safety margin to account for duct losses, dust filter loading, and future process changes. For the example above: 43,200 × 1.15 = 49,680 m³/h total. If using 8 ceiling or wall fans: 49,680 ÷ 8 = 6,210 m³/h per unit — select the next standard size up.

Common Mistakes to Avoid

  • Ignoring the height. Many designers use floor area only and forget that ACH is a volume ratio. A tall warehouse with 12 m ceilings has 3× the volume of a 4 m ceiling building at the same floor area.
  • Not adding the safety margin. New fans are efficient; after 2-3 years of dust loading, pressure drop increases and actual airflow drops 10-15%.
  • Forgetting local extraction. ACH alone is insufficient for welding and chemical fume. Local hoods or extraction points must supplement the general ventilation to keep the worker breathing zone clean.
  • Wrong fan classification. For factory-wide ACH targets, axial fans (low static pressure) are more efficient than centrifugal fans. Use centrifugal or blowers only where high-duct static pressure is present.

When to Use Keruite Engineering Support

If your workshop has multiple process zones, high-temperature heat loads, or specific fume hazards, a basic ACH calculation may not capture the full system requirements. Keruite's engineering team provides free airflow calculations, CFD layout support, and product selection to ensure the final system meets both the air quality and energy efficiency targets of your project.

Request a free ventilation calculation →

Share this article:

Need Help Selecting the Right Equipment?

Our engineering team provides free consultation on fan selection, system design, and technical specifications.

Request a Technical Proposal Browse Products

Related Articles

ATEX / IECEx Explosion-Proof Ventilation: A Practical Guide ... →